We broke ground on November 29th, 2017. The idea was (and still is, I guess) to build the addition ourselves so that we would appreciate every little bit that was added. If we hired it out, we could leave for a week, come back and it would be complete! But would we appreciate that?
After 4 years, I think we would have been just fine. 🙂



11/24/2017 
11/29/20 – Propane line moved 
11/30/2017 – Owen fulfilling childhood dream (driving an excavator) 
12/14/2017 – Pouring footer 
4/26/2018 – Had to wait for spring 
6/2/2018 – Had to dig more out 
8/19/2018 – Took so long to move the A/C, grass grew in. 
8/23/2018 
8/30/2018 
8/9/2018 – Had to match the height to the existing house 
9/8/2018 
9/9/2018 
9/26/2018 – Thank you Michael for helping me with the roof framing! 
9/27/2018 – House addition / play stage for the girls 
9/29/2018 – I got it straightened out eventually. 
10/21/2018 – Sheathing 
11/11/2018 
11/22/2018 – Thanksgiving 
3/9/2019 – Roof installed, cut into the house! 
5/10/2019 – Pause to build porch and install hot tub 
9/14/2019 
9/14/2019 Reworked plumbing for the old house 
9/26/2019 – Windows! 
10/12/2019 – More windows! 
11/23/2019 – Happy Thanksgiving! 
11/25/2019 – Cut into second floor 
11/26/2019 – Interior framing 
11/27/2019 Upgraded electrical service 
11/28/2019 – Wiring in the crawlspace 
12/21/2019 – Testing the lights! 
2/7/2020 Addition waste plumbing 
2/9/2020 – Tied into existing waste line 
2/29/2020 Soffits, gable work 
4/26/2020 
5/24/2020 
6/2/2020 – Filling in the old well pit 
6/23/2020 Master shower 
6/27/2020 Upstairs shower 
6/27/2020 Utilities transition from old house to new 
6/28/2020 Gluing the shower 
7/1/2020 New water supply complete! 
8/7/2020 Drywall complete 
8/8/2020 Priming 
8/13/2020 Flooring 
8/15/2020 Pause to refinish old house flooring 
8/15/2020 Repairs 
8/16/2020 – Filler 
8/19/2020 Mini Split! 
8/20/2020 – Mini split installed 
8/20/2020 Mini split installed 
8/27/2020 
8/28/2020 
8/28/2020 
8/30/2020 
9/2/2020 
9/5/2020 – Needed a new front porch… 
9/19/2020 Upstairs bathroom floor 
9/19/2020 Fixtures 
10/3/2020 Bedroom floor 
10/17/2020 – Ikea wardrobes 
10/23/2020 
11/29/2020 Coat closet 
12/5/2020 – Siding 
12/19/2020 
1/20/2021 Carpet! 
1/20/2021 
1/20/2021 
1/20/2021 Office / guest room 
1/21/2021 Play room with opening to addition 
1/21/2021 Second floor hallway 
1/21/2021 Second floor office / guest room